A Method for Composite Power System Reliability Evaluation Based on Delivery Point Capability Model
Zhu Jinzhou1, Zhang Yan1, Wang Saiyi2, Hua Yueshen2
1. School of Electronic Information and Electrical Engineering Shanghai Jiao Tong University Shanghai 200240 China; 2. State Grid Shanghai Municipal Electric Power Company Shanghai 200122 China
Abstract:The efficiency of the composite power system (CPS) reliability evaluation can be improved effectively by using the decoupling characteristics between CPS transfer capability and corresponding load (system-load decoupling). There are still some technical defects in the existing methods based on system-load decoupling. Existing transfer capability calculation models consider neither the optimal load shedding under abnormal conditions nor the change of the load level of each delivery point. In addition, there are few researches on the calculation methods of frequency and duration reliability index. By using the system-load decoupling characteristics, a method for CPS reliability evaluation based on delivery point capability model is proposed. Firstly, an optimal decision-making model is presented for calculating delivery points transfer capability of CPS, which is suitable for reliability evaluation. Given that the objective function of the presented optimal model has successively increasing slopes, the corresponding nonlinear model is transformed into a linear programming model to be solved to enhance the computational efficiency. Then, the probability-frequency distribution function of delivery point transfer capability, also named delivery point capability model, is built based on Markov chain by extending the concept of state probability and incremental frequency already used for modeling available capability of generation. Not only the probability but also the frequency and duration reliability index of delivery points and CPS can be obtained by convolution and addition operation between delivery point capability models and corresponding load models. The analysis for RBTS-6 test system demonstrates the validity of the proposed method.
祝锦舟, 张焰, 王赛一, 华月申. 基于传输点容量模型的发输电系统可靠性评估[J]. 电工技术学报, 2018, 33(1): 92-103.
Zhu Jinzhou, Zhang Yan, Wang Saiyi, Hua Yueshen. A Method for Composite Power System Reliability Evaluation Based on Delivery Point Capability Model. Transactions of China Electrotechnical Society, 2018, 33(1): 92-103.
[1] Billinton R, Wangdee W. Delivery point reliability indices of a bulk electric system using sequential Monte Carlo simulation[J]. IEEE Transactions on Power Delivery, 2006, 21(1): 345-352. [2] 赵渊, 周家启, 刘志宏. 大电网可靠性的序贯和非序贯蒙特卡洛仿真的收敛性分析及比较[J]. 电工技术学报, 2009, 24(11): 127-133. Zhao Yuan, Zhou Jiaqi, Liu Zhihong. Convergence analysis and comparison of sequential and nonsequential Monte-Carlo simulation for bulk power system reliability assessment[J]. Transactions of China Electrotechnical Society, 2009, 24(11): 127-133. [3] 蒋程, 王硕, 王宝庆, 等. 基于拉丁超立方采样的含风电电力系统的概率可靠性评估[J]. 电工技术学报, 2016, 31(10): 193-206. Jiang Cheng, Wang Shuo, Wang Baoqing, et al. Probabilistic reliability assessment of power system containing wind power based on Latin Hypercube sampling[J]. Transactions of China Electrotechnical Society, 2016, 31(10): 193-206. [4] 王杨, 谢开贵, 胡博, 等. 基于时序模拟的离网型微网可靠性分析[J]. 电工技术学报, 2016, 31(6): 206-211. Wang Yang, Xie Kaigui, Hu Bo, et al. Reliability analysis of islanded microgrid based on sequential simulation[J]. Transactions of China Electrotechnical Society, 2016, 31(6): 206-211. [5] 赵渊, 周家启, 周念成, 等. 大电力系统可靠性评估的解析计算模型[J]. 中国电机工程学报, 2006, 26(5): 19-25. Zhao Yuan, Zhou Jiaqi, Zhou Niancheng, et al. An analytical approach for bulk power systems reliability assessment[J]. Proceedings of the CSEE, 2006, 26(5): 19-25. [6] Billinton R, Wang P, Zhang W. Reliability assessment of an electric power system using a reliability network equivalent approach[C]// WESCANEX 97: IEEE Communications, Power and Computing, Conference, 1997, 17(3): 53-58. [7] Wang P, Billinton R, Goel L. Unreliability cost assessment of an electric power system using reliability network equivalent approaches[J]. IEEE Transactions on Power Systems, 2002, 17(3): 549-556. [8] Choi J, Billinton R, Futuhi-Firuzabed M. Development of a nodal effective load model considering transmission system element unavailabilities[J]. IEE Proceedings - Generation Transmission and Distribution, 2005, 152(1): 79-89. [9] Choi J, Mount T D, Thomas R J, Billinton R. Probabilistic reliability criterion for planning transmission system expansions[J]. IEE Proceedings -Generation Transmission and Distribution, 2006, 153(6): 719-727. [10] Choi J, Tran T, Kwon J, et al. Nodal probabilistic production cost simulation considering transmission system unavailabilty[J]. IET Generation Transmission and Distribution, 2008, 2(1): 32-42. [11] Cho K, Park J, Oh T, Choi J, et al. Probabilistic reliability criterion for expansion planning of grids including wind turbine generators[C]//Power and Energy Society General Meeting,IEEE, 2011,19(5): 1-6. [12] Cho K, Park J, Choi J. Probabilistic reliability based grid expansion planning of power system including wind turbine generators[J]. Journal of Electrical Engineering and Technology, 2012, 7(5): 698-704. [13] 赵渊, 张进, 芦晶晶, 等. 大电网可靠性评估的卷积计算模型[J]. 电网技术, 2013, 37(9): 2466-2473. Zhao Yuan, Zhang Jin, Lu Jingjing, et al. A convolution model for bulk power grid reliability evaluation[J]. Power System Technology, 2013, 37(9): 2466-2473. [14] 谈天夫, 高山, 李海峰, 等. 考虑负荷分布变化的改进组合电力系统等效负荷持续曲线法[J]. 电力自动化设备, 2014, 34(12): 44-51. Tan Tianfu, Gao Shan, Li Haifeng, et al. Improved composite power system equivalent load duration curve method considering variation of load distribution [J]. Electric Power Automation Equipment, 2014, 34(12): 44-51. [15] 刘洋, 周家启. 大电网可靠性评估最优负荷削减模型[J]. 重庆大学学报: 自然科学版, 2003, 26(10): 52-55. Liu Yang, Zhou Jiaqi. Optimal load curtailment in bulk power system reliability evaluation[J]. Journal of Chongqing University, 2003, 26(10): 52-55. [16] Billinton R, Goel L. Overall adequacy assessment of an electric power system[J]. IEE Proceedings C - Generation Transmission and Distribution, 1992, 139(1): 57-63. [17] Billinton R, Satish J. Adequacy evaluation in generation, transmission and distribution systems of an electric power system[C]//WESCANEX 93 'Communications, Computers and Power in the Modern Environment.' Conference Proceedings, IEEE, Saskatoon, Sask, Canada, 1993: 120-126. [18] Wang X F, Pottle C. A concise frequency and duration approach to generating system reliability studies[J]. IEEE Transactions on Power Apparatus and Systems, 1983, 102(8): 2521-2530. [19] Leite da Silva A M, Melo A C G, Cunha S H F. Frequency and duration method for reliability evaluation of large-scale hydrothermal generating systems[J]. IEE Proceedings C - Generation, Transmission and Distribution, 1991, 138(1): 94-102. [20] Renuga P, Ramaraj N, Primrose A. Frequency and duration method for reliability evaluation of large scale power generation system by fast fourier transform technique[J]. Journal of Energy and Environment, 2006, 5: 94-100. [21] Leite da Silva A M, Fernández R A G, Singh C. Generating capacity reliability evaluation based on Monte Carlo simulation and cross-entropy methods[J]. IEEE Transactions on Power Systems, 2010, 25(1): 129-137. [22] Grijalva S, Sauer P W, Weber J D. Enhancement of linear ATC calculations by the incorporation of reactive power flows[J]. IEEE Transactions on Power Systems, 2003, 18(2): 619-624. [23] Bertsekas D P. Nonlinear Programming[M]. 2nd ed. Belmont, MA: Athena Scientific Press, 1999. [24] 李士勇. 智能优化算法原理与应用[M]. 哈尔滨: 哈尔滨工业大学出版社, 2012. [25] 李志平, 李文沅, 徐国禹. 具有递增斜率的分段线性规划的解法. 重庆大学学报, 1989, 12(5): 35-42. Li Zhiping, Li Wenyuan, Xu Guoyu. An algorithm of piecewise linear programming with successively increasing slopes[J]. Journal of Chongqing University, 1989, 12(5): 35-42. [26] 李文沅, 李志平, 徐国禹. 递增斜率分段线性规划的对偶算法[J]. 重庆大学学报, 1991, 14(1): 6-11. Li Wenyuan, Li Zhiping, Xu Guoyu. A dual algorithm of piecewise linear programming with successively increasing slopes[J]. Journal of Chongqing University, 1991, 14(1): 6-11. [27] Billinton R, Allan R N. Reliability evaluation of power systems[M]. 2nd ed. New York: Plenum, 1996. [28] 谷云东, 张素杰, 冯君淑. 大用户电力负荷的多模型模糊综合预测[J]. 电工技术学报, 2015, 30(23): 110-115. Gu Yundong, Zhang Sujie, Feng Junshu. Multi-model fuzzy synthesis forecasting of electric power loads for larger consumers[J]. Transactions of China Electrotechnical Society, 2015, 30(23): 110-115. [29] Billinton R, Kumar S, Chowdhury N, et al. A reliability test system for educational purposes-basic data[J]. IEEE Transactions on Power Systems, 1989, 4(3): 1238-1244. [30] 吴喜之, 赵博娟. 非参数统计[M]. 2版. 北京: 中国统计出版社, 2009.