Abstract:The 35kV/121MVA superconductor cable and 35kV/90MVA superconductor fault current limiter at Yunnan Puji substation of southern china power grid have put into operation more than 8 years and 4 years respectively. A lot of operation data and experience have been accumulated. After several years operation and long-term monitoring, the main electric parameters of superconductor cable are the stable as the first, such as DC resistance, insulation etc. Except the individual parameter is not the same as the original design, the main thermal parameters have been working consistently, the cooling system is basically normal for a long time. The open cooling system is designed for the superconductor fault current limiter, and the operation parameters and liquid nitrogen consumption are the same as designed. Because the liquid nitrogen cooling system and demonstration stage, the reliability of prototype model of superconductor power equipment is lower. Maintenance experience proves that the reliability of cooling system and the optimization of the whole system are the main aspects to determine the reliability of the HTS power devices. Data of operation, test and maintenance of the two sets of HTS power equipment are reported and analyzed in this article. It will provide important reference for the research and application of HTS power equipment.
任安林, 田密, 字美荣, 崔继斌. 普吉变电站超导电力设备运行分析[J]. 电工技术学报, 2012, 27(10): 86-90.
Ren Anlin, Tian Mi, Zi Meirong, Cui Jibin. The Operation Research and Analysis of Superconductor Power Equipment at Yunnan Puji Substation. Transactions of China Electrotechnical Society, 2012, 27(10): 86-90.
[1] Xin Ying, Hou Bo, Bi Yanfang, et al. Introduction of China’s first live grid installed HTS power cable system[C]. IEEE Transactions on Applied Supercon- ductivity, 2005, (6): 1814-1817. [2] Xin Y, Gong W Z, Niu X Y, et al, Manufacturing and test of a 35kV/90MVA saturated iron-core type superconductive fault current limiter for live-grid operation[C]. ASC, 2008: 1934-1937. [3] 杨军, 张哲, 尹项根, 等, 我国首套高温超导电缆并网运行情况[J]. 电网技术, 2005, 29(4): 4-7. Yang Jun, Zhang Zhe, Yin Xianggen, et al. On-line operation situation of first high temperature superconducting cable system in China[J]. Power System Technology, 2005, 29(4): 4-7. [4] 张羿, 任安林, 田密, 等. 超导电力数据监测平台技术架构与实现[J]. 电气自动化, 2011, 33(5): 61-64. Zhang Yi, Ren Anlin, Tian Mi, et al. The framework and realization of superconductor power data monitor platform technology[J]. Electrical Automation, 2011, 33(5): 61-64. [5] 侯波, 叶锋, 熊志全, 等. 我国第一组高温超导电缆的运行工况及损耗计算[J]. 电网技术, 2006, 30(14): 24-29. Hou Bo, Ye Feng, Xiong Zhiquan, et al. Operation analysis for the Chinese first high temperature superconductor (HTS) power cable system[J]. Power System Technology, 2006, 30(14): 24-29.